ADDITIONAL WATER SOURCE PROJECT- WELL 11

The installation of Sheep Creek Water Company's Well 11 was approved by the Shareholders at the Annual Shareholder Meeting in May 2017.  The Board of Directors have been pushing to complete this project. 

The Board approved the well drilling contractor Layne from Redlands, California.  Layne began work on March 28, 2018.  As of April 18, 2018, the pilot hole has been drilled to 1,520 feet and is awaiting well design before the hole is bored for casing.  The well is drilled by reverse circulation method, which requires the hole to be full of water the entire time during drilling. 

See Current Projects for more information